Andover Road Update:
Due to construction, traffic continues to be congested on North Andover Road. Not surprising, congestion is the worst from 7:15 a.m. - 8:15 a.m. & 2:30 p.m. - 3:30 p.m., Monday - Friday. If you do not need to be on North Andover Road to take a student to school or report to work along that stretch, it is recommended you find an alternate route.
The asphalt milling of Andover Road has been completed and the existing cracks in the pavement are currently being patched. Once the patching is completed the entire roadway will be overlaid starting next week, then the permanent pavement markings will be installed.
The footings for the permanent signals are being installed now and soon the permanent signals at the Allison intersection and the north school drive will be installed. The overall project is scheduled to be completed by the end of 2022. Thank you for your continued patience as we work to improve this roadway!
Original source can be found here